NASA could not launch its Artemis 2 moon mission just some weeks from now in any case.
After in a single day knowledge confirmed an interruption in helium circulate within the SLS interim cryogenic propulsion stage, groups are troubleshooting and making ready for a probable rollback of Artemis II to the VAB at @NASAKennedy. This can virtually assuredly affect the March launch window. @NASA will…February 21, 2026
“This can virtually assuredly affect the March launch window,” Isaacman said.
That window is relatively short. It runs from March 6 through March 9, with another opportunity on March 11. If Artemis 2 can’t hit any of those dates, NASA will have to wait at least three additional weeks: The next window features target launch dates of April 1, April 3-6 and April 30.
“A rollback would mean NASA will not launch Artemis 2 in the March launch window,” NASA officials wrote in a blog post on Saturday. “Nonetheless, the short preparations allow NASA to probably protect the April launch window if a rollback is required, pending the end result of knowledge findings, restore efforts, and the way the schedule involves fruition within the coming days and weeks.”
Saturday’s information was one thing of a shock. It got here only a day after NASA introduced that it was focusing on March 6 for the launch of Artemis 2, the primary crewed mission past low Earth orbit for the reason that finish of the Apollo period. Artemis 2 will ship three NASA astronauts and one Canadian on a roughly 10-day journey round the moon and again to Earth in a Orion capsule.
The company made the March 6 name after reviewing knowledge from Artemis 2’s second moist gown rehearsal (WDR), a two-day-long follow run of the key operations main as much as launch.
The WDR wrapped up on Thursday (Feb. 19) with a profitable fueling of each SLS phases. This was a giant milestone for the Artemis 2 workforce, which needed to terminate the mission’s first WDR early on Feb. 2 resulting from a leak of liquid hydrogen (LH2) propellant.
LH2 leaks plagued Artemis 1, delaying the launch of that finally profitable uncrewed moon mission a number of instances again in 2022. However NASA appears to now have the difficulty underneath management.
Throughout a press convention on Friday, Artemis 2 workforce members mentioned there have been simply a few massive packing containers left to test earlier than giving the mission a inexperienced gentle to launch.
One was the completion of the flight readiness overview, which was anticipated to happen late this coming week. The opposite was the set up of two “contingency pad entry” trusses on the SLS’ cellular launch tower, which is able to permit groups to test Artemis 2’s flight termination system on the pad.
These trusses have been put in on Friday, NASA officers wrote in Saturday’s weblog put up. However they will most likely be eliminated quickly.
“Groups are actively reviewing knowledge, and taking steps to allow rollback positions for NASA to deal with the difficulty as quickly as potential whereas engineers decide the very best path ahead,” officers wrote within the replace.
“As a way to defend for troubleshooting choices at each Pad B and the VAB, groups are making preparations to take away the pad entry platforms put in yesterday, which have wind-driven constraints and can’t be eliminated throughout excessive winds, that are forecasted for tomorrow,” they added.
Correct helium circulate is significant to the right functioning of the SLS higher stage; it pressurizes the LH2 and liquid oxygen propellant tanks and helps preserve “the right environmental circumstances” for engine operation, in line with the weblog put up. The circulate problem was not seen through the WDR.
Editor’s observe: This story was up to date at 2:15 p.m. ET on Feb. 21 with extra particulars from NASA’s weblog put up, which itself was up to date.